Photos of Project Updates
Progress from April through November 2013 on both the east and west sides of the stadium.
East side sink hole work | West side bleacher and wall repair/replacement |
The east side work is a project by State College Borough. They dug to find both the throat of the sinkhole and also a solid foundation for building a reverse filter and water conveyance system. They maintained the current water conveyance structure to handle any storms that may arrive until they are ready to rebuild. The new conveyance system is now being built. | The west side work involves bleacher removal and excavation and rebuilding the retaining wall and then replacing the bleachers, sidewalk, and stonework. |
October 24, 2013 More sidewalk is installed | |
October 11 2013 Special detail planned for corner of Fairmount & Fraser Sts. | |
October 3, 2013 Sidewalk partially completed. | |
September 27, 2013 Sidewalk being laid. | |
September 6, 2013 Preparing for the first home football game. | |
September 5, 2013 West side bleachers are being installed. | |
August 29, 2013 Bleachers begin to be installed. | |
August 12, 2013 Football practice is able to take place while construction continues. | |
August 5, 2013 A layer of sand is applied to the turf as part of the installation. | |
August 2, 2013 Concrete is poured in the northeast corner. | |
July 31, 2013 The artificial turf goes in and the S is applied. | |
July 29, 2013 The artificial turf is being installed. | |
June 13, 2013 | June 13, 2013 |
June 6, 2013 | June 6, 2013 |
May 16, 2013 | May 16, 2013 |
May 6, 2013 | May 6, 2013 |
May 2, 2013 | May 2, 2013 Preparing for the westside wall repair. |
April 19, 2013 | April 19, 2013 |
April 18, 2013 With the help of Alpha Fire Company we blasted 1,500 gpm of water into the sinkhole for 15 minutes April 18. There was no refusal of water and it appeared to be capable of accepting at least double or triple that rate. Building of the filter (rock installation) will begin soon. | April 18, 2013 Workers prepare to remove one of the lights on the west side of the stadium so they can continue work on the west side wall area. |
April 17, 2013 | April 17, 2013 |
April 16, 2013 | April 16, 2013 |
April 12, 2013 | April 12, 2013 |
April 9, 2013 | April 9, 2013 |
April 8, 2013 | April 8, 2013 |
April 5, 2013 | April 5, 2013 |
April 4, 2013 | April 4, 2013 |