January 2016-January 2018: Phase 1
New construction in South parking lot, classes in existing buildings
 
January 2018-June 2018: Phase 2
Renovations and additions to old portions of South building, classes in new portions South building and old North building
 
June 2018-July 2019: Phase 3
Demolition and new construction at North building, classes are phased into completed, new High School
 
Summer 2019
Project completion