Community Input
State High Project Blog
Trailer News:
-
The positive is that the electric and safety items all passed
-
Only item not to pass is insulation
-
Inspection is scheduled for Wednesday (stay tuned)
-
Cleaning of trailers will continue this weekI am looking forward to having the trailers in our rearview mirror.
General News:
-
Concrete pours for slab on deck will occur this Wednesday and Thursday in Pods “A” and “D”
-
Transition from underground utilities in connector area (outside of library and science rooms) continues
-
Electrical Conduit continues to be laid and cement poured over
-
Rock hammering will continue as more rock is in the way of the conduit installation
South News:
-
Trailers work is continuing
-
A variety of tasks to be completed as well as code compliance and inspection are on order
-
Completion Target: the week of 9/19
-
Work closest to the South Library (if you haven’t been to the South library to take a look, it is worth your time)
-
Concrete retaining wall is for the main mechanical wall
-
On top of that wall will be the floor of the new gym (hard to believe)
- Area to the right of that will be the student success lab, roar store, cafe, and counseling office
- Area beyond the wall will be classrooms and the media center (library)
North News:
-
Trailers work is continuing
-
A variety of tasks to be completed as well as code compliance and inspection are on order
-
Completion Target: the week of 9/12
General News:
-
Project continues on schedule with similar work on foundations, masonry, mechanical rough-ins, steel work… many workers are on site
This will be the flow for the first day of school, scroll down for the traffic flow until 8/29
Student drop-off is via the Logan Ave. entrance.
South News:
- work continues on the 4 pods and progress is seen daily
- demolition work on lower parts of the South has occurred and utility work continues
- back lot and exit lane will be paved tomorrow (weather permitting)
- parking lot line striping will take place some time late this week or early next week (weather permitting)
- Modular classrooms:
- working on finishing touches of interior and installation
- looking to finish cleaning and move furniture in through next weekend
- waiting on West Penn Power to arrive and connect electric and installation of ramps
- as CJ’s email mentioned, contingency plans are prepared if we are not in the trailers on the 29th
- we were in the trailers this week and they are going to be very nice, comfortable spaces when complete
North News:
- Modular classrooms: (same as South)
- working on finishing touches of interior and installation
- looking to finish cleaning and move furniture in through next weekend
- waiting on West Penn Power to arrive and connect electric and installation of ramps
- as CJ’s email mentioned, contingency plans are prepared if we are not in the trailers on the 29th
General News:
- overall work is still on schedule despite the rainy weather as of late