Skip To Main Content

Community Input

State High Project Blog

Trailer News:
  • The positive is that the electric and safety items all passed
  • Only item not to pass is insulation
  • Inspection is scheduled for Wednesday (stay tuned)
  • Cleaning of trailers will continue this week
     
    I am looking forward to having the trailers in our rearview mirror.

 

General News:
  • Concrete pours for slab on deck will occur this Wednesday and Thursday in Pods “A” and “D”
  • Transition from underground utilities in connector area (outside of library and science rooms) continues
  • Electrical Conduit continues to be laid and cement poured over
  • Rock hammering will continue as more rock is in the way of the conduit installation

 

South News:
  • Trailers work is continuing
    • A variety of tasks to be completed as well as code compliance and inspection are on order
    • Completion Target: the week of 9/19
  • Work closest to the South Library (if you haven’t been to the South library to take a look, it is worth your time)
    • Concrete retaining wall is for the main mechanical wall
    • On top of that wall will be the floor of the new gym (hard to believe)
    • Area to the right of that will be the student success lab, roar store, cafe, and counseling office
    • Area beyond the wall will be classrooms and the media center (library)

 

North News:
  • Trailers work is continuing
    • A variety of tasks to be completed as well as code compliance and inspection are on order
    • Completion Target: the week of 9/12

 

General News:
  • Project continues on schedule with similar work on foundations, masonry, mechanical rough-ins, steel work…  many workers are on site

 

South News:
  • work continues on the 4 pods and progress is seen daily
  • demolition work on lower parts of the South has occurred and utility work continues
  • back lot and exit lane will be paved tomorrow (weather permitting)
  • parking lot line striping will take place some time late this week or early next week (weather permitting)
  • Modular classrooms: 
    • working on finishing touches of interior and installation
    • looking to finish cleaning and move furniture in through next weekend
    • waiting on West Penn Power to arrive and connect electric and installation of ramps
    • as CJs email mentioned, contingency plans are prepared if we are not in the trailers on the 29th
    • we were in the trailers this week and they are going to be very nice, comfortable spaces when complete

 

North News:
    • Modular classrooms: (same as South)
      • working on finishing touches of interior and installation
      • looking to finish cleaning and move furniture in through next weekend
      • waiting on West Penn Power to arrive and connect electric and installation of ramps
      • as CJs email mentioned, contingency plans are prepared if we are not in the trailers on the 29th
 

 

General News:
  • overall work is still on schedule despite the rainy weather as of late